Orlando Perilla v. University of Massachusetts Building Authority (SPR 20251349)

Massachusetts Public Records Appeal · Petitioner won — agency ordered to respond · Filed 05-20-2025

ClosedAppealPetitioner Won

SPR 20251349 is a Massachusetts Public Records Law appeal filed by Orlando Perilla concerning records held by University of Massachusetts Building Authority, opened 05-20-2025. Type: Appeal. Status: Closed. Supervisor of Public Records determination: Petitioner won — agency ordered to respond.

Case Details

Case Number
20251349
Case Type
Appeal
Case Subtype
Initial
Status
Closed
Requester
Orlando Perilla
Custodian
University of Massachusetts Building Authority
Date Opened
05-20-2025
Date Closed
06-04-2025
Date Request Submitted
03-07-2025
Response Provided Date
05-12-2025
Processing Fees Charged
0.00
Petitions Regarding Fees
No
Went to Court
No

PDF Document

Extracted Text (searchable & copyable)

The Commonwealth of Massachusetts William Francis Galvin, Secretary of the Commonwealth Public Records Division Manza Arthur Supervisor of Records June 4, 2025 SPR25/1349 David P. Mullen, Esq. Deputy Director/General Counsel Director of Capital Projects University of Massachusetts Building Authority UMass Amherst at Mt. Ida Campus 100 Carlson Avenue Newton, MA 02459 Dear Attorney Mullen: I have received the petition of Orlando Perilla, of Harbor Point Community Task Force, appealing the response of the University of Massachusetts Building Authority (UMBA) to a request for public records. See G. L. c. 66, § 10A; see also 950 C.M.R. 32.08(1). On March 7, 2025, Mr. Perilla requested “... copies of the following records ... related to University of Massachusetts Boston campus and/or UMBA’s Dorchester Bay City property located at the Bayside Expo Center site”: [1] All invoices from Mintz, Levin, Cohn, Ferris, Glovsky and Popeo, P.C received Since Accordia Partners was chosen to be Dorchester Bay City’s Developer for UMBA, and records of payments made thereon. [2] All development agreements between UMBA’s development partner Accordia Partners, and their affiliates. [3] All Dorchester Bay City developer-related contracts and contractor agreement extensions. [4] All third-party market assessments as they relate to the development of commercial and retail at Dorchester Bay City, including projected rental rates. [5] All in-house or third-party rental market studies and or assessments as they relate to the development of rental housing at Dorchester Bay City, including projected rental rates. [6] All evidence of the regulatory procedures that were required to approve all development agreements and contracts. [7] All third-party reports relating to Dorchester Bay City’s impact on climate resiliency, berm protection, and wave propagation. [8] All third-party and internal reports relating to UMBA’s interest in developing One Ashburton Place, Room 1719, Boston, Massachusetts 02108 • (617) 727-2832• Fax: (617) 727-5914 sec.state.ma.us/pre • pre@sec.state.ma.us

David P. Mullen, Esq. SPR25/1349 Page 2 June 4, 2025 the R2 parcel. [9] All Memoranda of Agreement, Memoranda of Understanding, and express written commitments to government agencies, local officials, and community groups. These commitments must include all organizations identified in the Massachusetts Environmental Policy Act (MEPA) filing including, but not limited to, UMBA, Department of Conservation & Recreation (DCR), Massachusetts Affordable Housing Alliance (MAHA), Columbia Savin Hill Civic Association, McCormack Civic Association, Boston Public Schools (BPS), Boston Parks and Recreation, Boys and Girls Club of Dorchester, the Martin Richard Foundation, and Boston Planning and Development Agency. [10] All invoices from McConnell Enterprises, Inc. and records of payments made thereon. [11] All invoices from VHB civil engineers and records of payments made thereon. [12] All invoices from Nitsch, Engineering, Inc. and records of payments made thereon. [13] All invoices from NV5 Global Inc. received over the past seven years and records of payments made thereon. [14] All invoices from BVH Integrated Services received and records of payments made thereon; and, [15] All invoices from Environmental Health & Engineering, Inc. received, and records of payments made thereon. Subsequently, on March 18, 2025, Mr. Perilla modified his request to only seek records responsive to Items 1 through 9 only. Prior Appeal The requested records were the subject of a prior appeal. See SPR25/0991 Determination of the Supervisor of Records (April 28, 2025). In my April 28th determination, it was my understanding that UMBA intended on providing a further response to Mr. Perilla. UMBA provided a response on May 12, 2025. Unsatisfied with UMBA’s response, Mr. Perilla petitioned this office and this appeal, SPR25/1349 was opened as a result. Subsequently, I learned that UMBA provided a further response on June 4, 2025. Where this appeal was opened as a result of UMBA’s May 12th response, I will now consider this administrative appeal closed. Mr. Perilla may appeal the substantive nature of UMBA’s June 4th response within ninety (90) days. See 50 C.M.R. 32.08(1).

David P. Mullen, Esq. SPR25/1349 Page 3 June 4, 2025 Sincerely, Manza Arthur Supervisor of Records cc: Orlando Perilla